Two private generating plants stopped producing at 4:43 p.m. on June 19, 2026, and the resulting partial blackout cut 170 MW of load and 119,323 CFE customers in Yucatán, Campeche, Quintana Roo, and Tabasco that afternoon, according to CFE’s statement that day; Expansión’s July 6, 2026 review of the event also lists Chiapas. A larger event followed on August 31, 2026, when two high-voltage lines dropped out and 745,533 customers across the Yucatán Peninsula and Chiapas lost power for close to seven hours; CFE attributed that one to vandalism. President Claudia Sheinbaum addressed the pattern publicly on June 24, 2026, and called them service interruptions. She attributed them to distribution failures and insufficient lines, and not to a generation shortfall. Mexican media and industry groups have been using the term apagones with increasing frequency. Whatever the label, some regions absorb this risk more than others. The Yucatán Peninsula has limited transmission capacity for importing power during peak demand, and Baja California runs an isolated grid with no interconnection to the national system, per the same reporting.
The financial record from the last comparable stress period is not abstract. The February 2021 winter grid crisis cost export manufacturers an estimated 2.7 billion dollars in lost production over two days, according to the export manufacturing council INDEX. In May 2024 CENACE declared an emergency operating state because operating reserves fell below 3%, against the 6% the system needs to run normally. The blackouts that month cost Jalisco’s industrial sector an estimated 200 to 250 million pesos, 12 to 15 million dollars, according to the Consejo de Cámaras Industriales de Jalisco. Individual food-sector companies in that state reported losses of up to 20 million pesos, about 1.2 million dollars, and a zinc producer in San Luis Potosí lost supply with its furnace loaded, per the Consejo Coordinador Empresarial. During the February 2021 event, INDEX put manufacturing losses at around 200 million dollars an hour across its member plants, and that figure reads as an order of magnitude and not a precise figure. The order of magnitude is the point.
Diesel generation has been the default answer to this risk for decades. For most industrial loads today it is the wrong default. A generator sized for backup sits idle the overwhelming majority of the year, earning nothing until the one day it is needed. Its fuel cost and maintenance burden climb every year it fails to amortize against daily use. Battery storage does something a standby generator cannot. It protects against the outage and it earns a return every single day it is not needed, by shifting load away from peak tariff hours and correcting the demand and power-factor charges that already dominate an industrial power bill. That dual function is the case for storage over backup generation. It also puts BESS in the capital budget alongside other investments, and out of the insurance line.
Why the grid keeps failing
The structural cause is a widening gap between how fast demand grows and how fast the grid that serves it expands. National electricity demand grew 3.4% in 2022 and 3.5% in 2023, while the transmission network grew just 0.09% and 0.10% in those same two years, according to the Mexican Institute for Competitiveness. CFE’s 2023 transmission investment ran at 21.7% of what its own planning estimate called for, per the same source. That gap does not close in a single budget cycle. It shows up first as a thin operating reserve margin, which fell below 3% in May 2024 against the 6% threshold the system needs for normal operation.
Drought compounded the shortfall in the 2023 to 2024 cycle. CFE’s hydroelectric output fell about 40% in 2023, and by May 2024 the El Novillo reservoir in Sonora stood at 11.2% of capacity and Huites in Sinaloa at 16.4%, per Excélsior’s reporting of CONAGUA data. That removed a source of flexible generation the system has historically leaned on during demand peaks. Eleazar Castro of the consultancy Elevation Ideas, quoted in Expansión’s July 2026 reporting, points to the same convergence of pressures. Summer demand spikes, planned plant maintenance, low reservoir levels, and heat waves all strain available capacity in the same window. None of these alone would be a crisis. Together, on a grid with limited redundancy in its circuit connections, they are. The redundancy point comes from the risk analysis firm Admonitor Energy Analytics, cited in the same reporting.
A BBVA Research survey of Asociación Mexicana de Parques Industriales Privados members, fielded in March 2023, found that 91% of the parks surveyed reported problems with their electricity supply. Outage risk is not a tail scenario to plan against. It is a near-certainty every industrial operator is already living with.
What an outage actually costs
Run the arithmetic a plant manager actually needs. A facility with 120 kW of critical load that loses power for two hours needs roughly 267 kWh of backup energy to ride through the outage and cover restart, at 90% system efficiency. The standard formula is critical load in kilowatts multiplied by required autonomy in hours, divided by system efficiency, as laid out in industry guidance on outage risk sizing published in June 2026. That is a modest number for a modern BESS to cover. The harder number to model is what an unprotected two hours costs in scrapped product, missed shipment windows, and restart losses. The Jalisco and San Luis Potosí figures above are the closest public benchmarks for what that runs at a mid-sized industrial operation.
Sizing backup against total connected load instead of critical load is what turns a 267 kWh requirement into a quote several times that size. Talk to an advisor.
The recurring, non-outage value of the same battery system is where the investment case gets easier to defend. That matters to a finance committee that has not yet seen a bad outage on its own line. Mexico Energy Partners’ published model for a 2 MW, 4 MWh battery at an installed cost of 25 million pesos cuts demand charges by 20%, saves about 3 million pesos a year, and gives a simple payback of 8.3 years before tax, financing, degradation, and maintenance effects. Payback ranges of 5 to 10 years circulate for industrial storage in Mexico, and they hold only under a stated tariff, demand share, and installed cost. A standby generator earns nothing in any of those years. That is the structural advantage over diesel. The same capital asset earns money on a normal Tuesday and still protects the line on the day the grid fails.
Why storage beats a diesel generator
Two Mexican manufacturers show the range of ways storage and onsite generation are being used to manage this exposure. Neither company frames its project as a backup purchase. DeAcero, the steel producer, signed a 20-year power purchase agreement with IEnova in March 2017 for the output of the 110 MW Pima Solar plant in Caborca, Sonora, a 115 million dollar investment by IEnova that was reported to cover roughly 20% of DeAcero’s energy requirement. Grupo Bimbo buys the output of the 90 MW Piedra Larga wind farm in Oaxaca under a long-term contract signed in 2012, plus 3.7 MW of rooftop solar PV across 33 sites in the first phase of its 2018 rooftop program. Both are large-scale, long-horizon commitments built around daily energy economics. Resilience is a byproduct.
That framing matters for how a plant should build its own business case. A BESS proposal pitched purely as insurance against the next emergency competes for budget against every other risk-mitigation request a finance committee sees, most of which do not pay for themselves. Pitch the same system as a demand-charge and tariff-optimization asset that also rides through an outage, and it competes as a capital project with a payback of 5 to 10 years on published Mexican inputs. That is a far easier conversation to win.
Tax treatment argues for moving now. The Plan México decree published in the Diario Oficial on January 21, 2025 allows an immediate deduction on new fixed assets bought through September 30, 2030, at rates that depend on the industry: 56% in 2025 and 2026 and 49% from 2027 to 2030 for electricity generation and distribution machinery, and 67% then 62% for food and beverage or auto parts manufacturers, for example. Separately, Article 34 of the income tax law already allows a 100% deduction for renewable generation and efficient cogeneration equipment. For a plant that can use the deduction against current-year income, that shortens the effective payback further.
What storage can’t solve
Duration is the limit. A battery system sized for a two- or four-hour outage does nothing for a multi-day event, and the February 2021 crisis and some of the 2024 disruptions ran longer than that. A plant in a region with genuinely poor grid redundancy should not treat storage alone as sufficient protection against the worst case. The Yucatán Peninsula’s import-constrained transmission and Baja California’s islanded system are the clearest examples. Diesel or natural gas backup still has a role for the tail risk that storage duration cannot economically cover. The right system is very often a hybrid.
There is also a real risk in over-sizing the system to the emergency case. A battery bought mainly for four-hour outage protection that a plant experiences twice a year will sit underused the other 363 days. That erodes the payback economics that make storage a better answer than diesel in the first place. Size the system from daily demand-charge and tariff-optimization value first, with outage coverage added as a secondary design constraint.
How to size the battery
Quantify your critical load first, not your total connected load. Identify the systems that must ride through an outage: refrigeration, continuous process lines, control systems. Size backup energy against that figure using the load-times-hours-divided-by-efficiency formula. Full plant capacity inflates the system size and the price tag for nothing. Under the Comisión Nacional de Energía’s storage rules published in the Diario Oficial on April 16, 2026, a battery behind the meter at a load center needs no storage permit as long as its power does not exceed the center’s demand and it exports no energy.
Model the daily value before the emergency value. Ask any storage proposal to quantify demand-charge reduction and tariff-shifting savings on its own, independent of outage protection. Confirm that number alone produces a payback inside the 5 to 10 year range Mexico Energy Partners has documented, with the tariff, demand share, and installed cost stated, before you credit any resilience benefit on top of it.
Match your backup duration to your actual regional risk. A plant on the Yucatán Peninsula or in Baja California, both flagged as structurally more exposed, should plan for longer-duration coverage or a hybrid system than a plant on a well-interconnected node in central Mexico.
Claim the accelerated depreciation window while it runs. The decree’s rates step down after December 31, 2026, from 56% to 49% for electricity machinery, for example, so a project delayed into 2027 captures a smaller deduction than the same project approved this year.
Solar and BESS Feasibility Study
Mexico Energy Partners sizes a battery or hybrid system against your metered critical load and your region's outage record, and states the payback in writing with its tariff, demand share, and installed cost inputs. Facility location, approximate demand, the loads that have to ride through an outage, and a short description of the current concern are enough to start, and no CFE bill is required. CFE bills and interval data come after the first conversation, under NDA.
Talk to a Mexico Energy Partners advisor or email info@mexicoenergypartners.com. Mexico Energy Partners sells no equipment and is compensated only by the client.
Sources
- June 19, 2026 outage at 4:43 p.m. after two private plants in the Sureste and Peninsular regions went offline, 170 MW of load and 119,323 customers in Yucatán, Campeche, Quintana Roo, and Tabasco. CFE statement, as reported by MVS Noticias, “CFE: apagón en el sureste afecta a más de 119 mil usuarios,” June 19, 2026.
- August 31, 2026 blackout: 745,533 customers (Yucatán 430,840; Quintana Roo 278,969; Chiapas 18,186; Campeche 17,538), close to seven hours, two high-voltage lines out, attributed by CFE to vandalism; five mass outages on the Peninsula in 18 months. Por Esto, “Cinco apagones masivos en año y medio acumulan más de 3 millones de afectaciones en la Península de Yucatán,” September 2, 2026.
- Yucatán Peninsula transmission constraints, Baja California’s isolated grid, and commentary from Eleazar Castro of Elevation Ideas and Admonitor Energy Analytics on converging demand, drought, and maintenance pressures and on limited circuit redundancy. Expansión, “¿Apagones o interrupciones en el servicio? Las razones que dejan sin luz a los mexicanos,” July 6, 2026.
- President Claudia Sheinbaum’s June 24, 2026 statement distinguishing service interruptions caused by distribution failures from generation shortfalls. Versión estenográfica, conferencia de prensa de la Presidenta, June 24, 2026, gob.mx/presidencia.
- February 2021 outages: 2.7 billion dollars of lost production over two days and around 200 million dollars an hour across INDEX member plants. INDEX president Luis Manuel Hernández, as reported by Expansión, February 16, 2021, and La Razón, February 17, 2021.
- May 2024 emergency operating state with reserves below 3% against the 6% requirement. Forbes México, “Sector eléctrico mexicano con bajo margen para operar,” May 16, 2024.
- Jalisco industrial losses of 200 to 250 million pesos (12 to 15 million dollars) from the May 2024 blackouts, Consejo de Cámaras Industriales de Jalisco, and food-sector losses of up to 20 million pesos per company, Cámara de la Industria Alimenticia de Jalisco. Mexico Business News, May 31, 2024, and El Economista, May 30, 2024.
- Zinc producer in San Luis Potosí that lost supply with its furnace loaded, Consejo Coordinador Empresarial. El CEO, “Empresarios y especialistas advierten más apagones para el verano,” May 27, 2024.
- National electricity demand growth of 3.4% (2022) and 3.5% (2023) versus transmission network expansion of 0.09% and 0.10%, and 2023 transmission investment at 21.7% of CFE’s own planning estimate. Instituto Mexicano para la Competitividad (IMCO), “Sin transmisión eléctrica no será posible acelerar la transición energética,” September 19, 2024.
- Hydroelectric output down about 40% in 2023 and reservoir levels at El Novillo (11.2%) and Huites (16.4%) in May 2024. Excélsior, “Hidroeléctricas se suman a crisis energética,” May 11, 2024, citing CONAGUA data.
- 91% of industrial parks surveyed reporting problems with electricity supply. BBVA Research and AMPIP member survey, March 2023, as reported by Cluster Industrial, July 25, 2023.
- Backup energy sizing methodology, critical load in kW multiplied by required autonomy in hours divided by system efficiency, with a 120 kW, two-hour, 90% efficiency, 266.67 kWh worked example. Ingeniería Real, “Apagones CFE 2026: impacto por sector y cómo proteger tu operación industrial,” June 30, 2026.
- Modeled 2 MW, 4 MWh battery at 25 million pesos installed, 20% demand-charge reduction, 3 million pesos a year in savings, 8.3-year simple payback, and the 5 to 10 year range that circulates in Mexico. Mexico Energy Partners, “When battery storage pays for a Mexican industrial plant,” March 15, 2025.
- DeAcero’s 20-year contract with IEnova for the 110 MW Pima Solar plant in Caborca, Sonora, a 115 million dollar investment. IEnova first-quarter 2017 earnings call, and PV Tech, March 28, 2017.
- Grupo Bimbo’s Piedra Larga wind farm, 90 MW, 45 turbines of 2 MW. Grupo Bimbo press release, October 30, 2012. Bimbo Solar first phase, 33 rooftop systems totaling 3.7 MW. Forbes México, February 1, 2018.
- Immediate deduction rates by activity, 2025 to 2026 and 2027 to 2030, for new fixed assets acquired through September 30, 2030. Decreto por el que se otorgan estímulos fiscales para apoyar la estrategia nacional denominada Plan México, Diario Oficial de la Federación, January 21, 2025. Ley del Impuesto sobre la Renta, Article 34, fraction XIII, 100% deduction for renewable generation and efficient cogeneration equipment.
- Storage rules: Disposiciones Administrativas de Carácter General para la integración de Sistemas de Almacenamiento de Energía Eléctrica al Sistema Eléctrico Nacional, Comisión Nacional de Energía, Diario Oficial de la Federación, April 16, 2026.